The Builders said they might not be with us tomorrow. The floor joists arrive on monday. So this could be the end of week 3!
First we have a make shift toilet pipe arrangement. so the can put concrete down the hole. This means I can shift the kitchen sink to its new home.. maybe!
They have tidied up the foundations so now there should be less mess to tread in the house.
I have built a few steps so the children can still get into the garden.
Finally we have connected the drains from the drive back up so if it rains it wont flood the extension. well thats the plan.